SAP Error Message - Details

  • Message type: E = Error

  • Message class: V4 - Nachrichten Verkauf (Variable Meldungen und EDI-Meldungen)

  • Message number: 232

  • Message text: L'appel n'est pas compatible avec l'appel horaire

  • Show details Hide details
  • Quelle est la cause de ce problème?

    In a scheduling agreement with delivery schedules, for which the
    just-in-time (JIT) and forecast delivery schedules are relevant for
    materials planning according to the validity of the JIT horizon, the
    delivery schedule quantity in the JIT delivery schedule horizon does
    not correspond to that in the JIT delivery schedule.
    However, the delivery schedule has a quantity in transit that has been
    included in the schedule line open quantities but is not included in
    the requirements.

    Le système émet un message d'erreur et ne vous permettra pas de poursuivre cette transaction tant que l'erreur n'est pas résolue.

    For example:
    Forecast dlv. sched Jan 1st JIT dlv. sched Feb 1st (valid to Feb 28)
    Cum. delivered qty 100 Cum. delivered qty 100
    Cum. received qty 10 Cum. received qty 50
    In transit 90 In transit 50
    Schedule lines Schedule lines Requirements
    Date Qty Open qty Date Qty Open qty
    ----------------------- ----------------------- ------
    Feb 1 20 0 0
    Feb 8 20 0 0
    Feb 15 20 10 10
    Feb 22 20 20 20
    Mar 1 100 10 100
    Apr 1 100 100 100
    The problem arises because on March 1, a requirement for 100 exists
    although the open quantity is only 10 when you look at the forecast
    delivery schedule only.
    However, if both delivery schedules are valid and relevant, the
    forecast delivery schedule should also contain a corresponding quantity
    for the February schedule lines in the JIT delivery schedule.
    At the moment, it is not clear to the system how much the customer
    requires for March 1.

    Réponse du système

    The system thinks that there are differences between the open
    quantities and the material planning requirements.

    Comment corriger cette erreur?

    You can do one of the following:
    Either change the material requirement processing for delivery
    schedules in the scheduling agreement.
    If you can't change the materials requirements processing, ask your
    customer to send you a new forecast delivery schedule that matches the
    JIT delivery schedule.
    If the customer can't send you a matching delivery schedule, you will
    have to adjust the delivery schedule, or enter a new forecast delivery
    manually.

    Procédure pour les administrateurs système


    Extrait du message d'erreur du système SAP. Copyright SAP SE.


AnswerBot

  • Quelle est la cause et la solution de l'erreur SAP V4232 - L'appel n'est pas compatible avec l'appel horaire ?




  • AnswerBot est une solution d'intelligence artificielle de tomco.ai.
    Disclaimer

Messages d'erreur SAP associés

Cliquez sur les liens ci-dessous pour voir les messages connexes suivants:


Les messages SAP se divisent en 3 catégories différentes : Messages d'erreur (type de message = E), Avertissements (W) ou Messages d'information (I).

Un message d'erreur vous empêchera de continuer votre travail - il s'agit d'un arrêt brutal et vous devez corriger l'erreur avant de pouvoir continuer. Un message d'avertissement arrêtera votre travail, cependant, vous pouvez alors contourner l'avertissement en appuyant sur la touche Entrée de votre clavier. Cela dit, il est toujours recommandé d'enquêter sur la cause du message d'avertissement et d'y remédier. Un message d'information n'arrêtera pas votre travail et est vraiment juste à des fins d'information.

Cliquez sur ce lien pour rechercher tous les messages SAP.