Message type: E = Error
Message class: C2 - Other messages production orders
Message number: 138
Message text: Order &: Subnetwork scheduled backwards
Teilnetze im Auftragsnetz werden mit RnckwSrtsterminierung terminiert.
Dies geschieht unabhSngig von der aktuellen Terminierungsart.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
The SAP error message C2138, which states "Order &: Subnetwork scheduled backwards," typically occurs in the context of production planning and scheduling within SAP. This error indicates that there is a scheduling conflict where the planned start time of a subnetwork (or operation) is set to occur before its predecessor operation has been completed. This can lead to inconsistencies in the production process, as operations cannot logically start before their prerequisites are finished.
Causes:
- Incorrect Scheduling Parameters: The scheduling parameters for the operations or networks may not be set correctly, leading to backward scheduling.
- Dependencies Not Defined: There may be missing or incorrectly defined dependencies between operations in the network.
- Resource Constraints: Resource availability might not be properly accounted for, causing the system to attempt to schedule operations in an illogical order.
- Manual Changes: Manual adjustments to the scheduling of operations may have inadvertently created a situation where operations are scheduled out of order.
Solutions:
- Check Operation Dependencies: Review the dependencies between operations in the network. Ensure that all predecessor and successor relationships are correctly defined.
- Adjust Scheduling Parameters: Verify and adjust the scheduling parameters for the operations. This includes lead times, setup times, and any other relevant parameters that could affect scheduling.
- Re-schedule the Order: Use the scheduling functions in SAP to re-schedule the order. This may involve using transaction codes like
CO02
(Change Production Order) orCM21
(Capacity Planning) to adjust the scheduling.- Review Resource Availability: Ensure that the resources required for the operations are available and that their availability is correctly reflected in the system.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on scheduling issues related to your version of SAP.
Related Information:
CO01
(Create Production Order), CO02
(Change Production Order), and CM21
(Capacity Planning) for managing production orders and scheduling.By addressing the underlying causes and following the suggested solutions, you should be able to resolve the C2138 error and ensure that your production scheduling is logical and efficient.
Sign up takes 1 minute. 7-day free trial.
C2137 Order &: Partial network scheduling with finish date as framework date
What causes this issue? The framework finish date for the subtree was not maint...
C2136 Status of released order is reverted to "Created"
What causes this issue? The routing was read in for the released order. It cann...
C2139 Application & does not allow you to take production versions into account
Self-Explanatory Message Since SAP believes that this specific error message is ...
C2140 Order &: Sales order & is assigned
What causes this issue? A sales order is assigned to the order. The setting in ...
SAP messages fall into 3 different categories: Error messages
(message type = E), Warnings (W) or Informational (I) messages.
An error message will prevent you from continuing your work - it is a hard stop and you need to fix the error before you can proceed. A warning message will stop your work, however, you can then bypass the warning by pressing the Enter key on your keyboard. That said, it is still good practice to investigate the cause of the warning message and address it. An information message will not stop your work and is truly just for informational purposes.
Click on this link to search all SAP messages.